Spaulding Youth Center – Board of Directors and Trustee Tour

In early November with the exterior shell and site work one hundred percent complete and the interior work well underway, CCI President and Project Manager, Jeff Downing led a tour for the Spaulding Youth Center Board of Directors and Trustees, accompanied by Spaulding Youth Center CEO & President Susan Calegari.

Despite starting the project over one month late due to spring road bans, the project is back on its original completion schedule and CCI estimates that the job may finish several weeks ahead of target if the last four months of construction go as planned.

CCI Superintendent Mark L’Heureux, reports that mechanical and electrical rough-in is 90% and drywall is well underway.  Permanent power and HVAC systems should be operational by the end of the month, allowing finishes to begin as scheduled. 

Stay tuned for more construction updates as progress continues over the next few months.